The building we are outfitting has Solar PV on site, an estimated 17,800kWh annual production. Half of it feeds a DC power Hydrogen electrolyzer that is used within the building and the other half is tied to reduce the building loads. Do I only count the half that is tied to the building or can I use all the energy produced by these panels to achieve the 2.5% or 5%?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
November 12, 2010 - 10:42 pm
What is the hydrogen used for? Does it offset power use in the building, or does it go to another purpose? If the former, I think you could count if you can provide calculations showing how it offsets annual energy costs.