See quotation from LEED-CI. "Use tenant renewable energy systems to offset the project’s energy cost. Calculate the project’s
percentage of renewable energy by the following equation:
% renewable energy = Equivalent cost of usable energy produced by renewable energy system/ Total building annual energy cost"
If the CS project fulfills the criteria for meeting maximum points on this credit and a lot of photovoltaics are installed, are the tenant obliged to install even more renewable energy sources? This doesn't seem correct.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5914 thumbs up
August 28, 2017 - 10:22 am
From the Reference Guide.
Projects whose base building uses renewable energy are eligible to receive credit for the percentage of its contribution. Use Equation 2 to determine this amount.
Equation 2. Equivalent cost of renewable energy from base building system
Equivalent cost of base building renewable energy = ($ value of renewable energy used in base building x % of base building energy delivered to project)