Schools-2009 EAc2: On-Site Renewable Energy
If a project installs a PV system but sells a SREC for that system can it still qualify for EA c2?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Can I pursue this credit if I am using one of the prescriptive compliance paths for EAp2/EAc1?
Can I really double-count onsite renewable energy in both EAc2 and EAc1?
Our PV system is being installed after the building is occupied. Is that okay?
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 1, 2011 - 9:40 pm
Yes, but there is a special clause that you need to buy additonal RECs. This is outlined in the LEED Reference Guide, if you have a copy. If not, we can probably paste it in here, or I think you can find it being discussed in the NC 2009 forum for this credit.