I have reviewed the websoilsurvey site at nrcs.usda.gov and half of our site boundary includes prime farmland. The half that is in the prime farmland category is also where we have located the detention/wetland for the project. More importantly, it is an in-town site. Any advice on whether this situation is acceptable to meet the SSc1 requirements?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
January 4, 2011 - 10:25 am
The requirement is that you can't develop hardscape on prime farmland. It sounds like you're not going to do that, although it depends on your stormwater design. Given what you've said so far, I'd say you meet the requirement.