Hi all,

Working on a project that had some old diesel and fuel tanks and lines on the site identified as APECs during Phase 1, so phase 2 was conducted by found no significant levels of contamination during bore-hole drilling and testing. The project is now in excavation, but has found significant soil contamination in areas previously unidentified which they are remediating.

In my opinion this qualifies it for Option 3, but my questions are:

Do you agree that this site qualifies for Option 3?

Does the environmental firm need to redo their Phase 2, or will the reports from the remediation be sufficient? The authority in charge is a bit murky because the owner of the site is also the municipal authority, but typically the provincial authority oversees contaminated sites.