NC-2009 EAc2:On-Site Renewable Energy

Owner Agent required information

Marcus, I am looking at the on-line form for EAc2 On-Site Renewable Energy. (LEED 2009 for New Construction) The asterisk occurs after each of two Required Signatory boxes. Path selected: Option 1 Whole Bulding Energy Simulation. Thanks!

4

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 11/29/2011 - 16:56

Under the Additional Details check the special circumstances box and a narrative space opens. Enter your explanation there for how the owner was informed about the ownership of the RECs and the installation of the system. If any documents would assist in this task, upload them.