I think you would have to submit as an alternative compliance path and hope for a positive response from the reviewer. Seems to me like it meets the intent.Not sure if this is practical, but could you delay your final application until three months post-occupancy and document it in the regular fashion?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Do I understand correctly that if we have outdoor air delivery monitoring on each of the AHU in the building then there is no need to separately monitor the air flow to the CI space we are fitting out?
If the base building AHU is monitored and you know for example it has 15% outside air. Then you can assume the amount of air delivered to your CI space also has 15% outside air. You may want to monitor or at least balance the airflow to your space to ensure that it is adequate.