Hi All

We are working in a project located in India which has an evaporative cooler as a cooling system, in the design submission review, the reviewer asked us to model the heating coil to control the humidity and to model the minimum fresh air in baseline case. In real time there is no heating coil present in the building. By now I had doubt that when considering onsite renewable energy whether I should consider the energy consumption including the heating coils, or the energy consumption of proposed design without humidity control (this is actual system installed in the project).