This is vaguely referenced in other posts, but I'm still confused: what is the level of detail we need to submit for our written Erosion & Sedimentation Control (ESC) plan? The example in the LEED Reference Guide shows a table with 6 strategies listed alongside their descriptions; the example SWPPP found through the EPA website is a 56 page document (http://www.epa.gov/npdes/pubs/exampleswppp_smallcommercial.pdf). That is a huge discrepancy! What is the level of detail that LEED is looking for in our submitted plans?

The civil engineer on our project put together a written plan complete with site drawings of silt fences, etc. and is expressing concerns about putting together a full SWPPP, which will understandably take up a great deal more of his time. Can we submit his one-page plan?