Our project contains a new LEED Building (addition) and Non-LEED Building (Existing, not in LEED Boundary). The school is looking into cross-tying the DDC controls (only) for the HVAC system for both portions in the new LEED Building. Is this accpetable per LEED as long as the 2 buildings have independendent energy use? There will be no energy impact here.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 11, 2011 - 2:53 pm
Yes, I would say so. If you already have the understanding that the addition can be certified by itself and comply with the MPRs, then I don't see how some control integration would really change the picture that much.