Dear LEED users
I would like to know, Is the ID credit 3 in HC 2009 design or construction credit, I found the ID P1 is a design credit but the ID c3 is a construction credit in the scorecard..! Is it possible?? Thanks
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Kim Lombard
Sustainability Leader and ArchitectAECOM
9 thumbs up
February 11, 2015 - 2:49 pm
It makes sense that it would be a construction credit since there are 12 meetings to document.
Susan Walter
HDRLEEDuser Expert
1299 thumbs up
February 12, 2015 - 2:10 pm
Correct, the pre-req is on the design team and the credit is on the construction team. One is a continuation of the other.