I believe the standard GBCI policy on sunset dates is six years from the last date that a project could register under the given rating system.

For CS and CI v2.0, I think those systems were current up until June 2009—right? I think that they hadn't gotten to v2.2, as NC had.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 03/13/2013 - 19:39

The rest of the v2 rating systems are set to sunset in June of 2015: -LEED-NC v2.2 – June 27, 2015 -LEED-CS v2.0 – June 27, 2015 -LEED-SCHOOLS v2007 – June 27, 2015 -LEED-CI v2.0 – June 27, 2015 -LEED-EBOM v2008 – June 27, 2015 More information about the sunset dates and requirements can be found in the LEED Certification Policy Manual (last updated: January 1, 2012).

Wed, 02/05/2014 - 16:21

Elizabeth, According to LEED CS v2.0 sunset date: you have to mail GBCI ( hard copy or CD) before 27/6/2015 for preliminary review as follow: 1- Standard review ( combined design and construction review): before the mentioned date 2- Separate design and construction review: for the design review you have to send design review before the sunset date and not later than 18 months to send construction review. GBCI address: Green Building Certification Institute Attn: LEED Certification Manager 2101 L Street NW, Suite 500 Washington, DC 20037