Hi,
On the credit form I must upload blower door test results but this credit is a design phase credit and the test is only after construction is complete. Can someone share how they solved this conflict?
Thanx
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
July 16, 2013 - 9:53 pm
A design phase credit does not have to be submitted at the design phase—it could be more appropriate to submit after construction, depending on your compliance path. I would simply submit after you have your testing results.
LILACH RAZ
August 4, 2013 - 3:27 am
Good Morning,
Our problem is that we have a design and construction compliance path. If we wouldn't supply the blower door test results, the credit's demands are not met.
Thanks
Peter Doo
PresidentDoo Consulting LLC
203 thumbs up
September 27, 2013 - 4:58 pm
You can defer the design credit review and submit it with the construction credits. As I recall, you simply do not mark it as complete.