If a project size is modified (the gross floor area) after the preliminary review, besides of the credits that have been attempted what other consequences do I have to consider?
Thanks
Forum discussion
CS-2009 PIf2: Project Summary Details
Hi
If a project size is modified (the gross floor area) after the preliminary review, besides of the credits that have been attempted what other consequences do I have to consider?
Thanks
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Jon Clifford
LEED-AP BD+CGREENSQUARE
LEEDuser Expert
326 thumbs up
April 22, 2017 - 10:30 pm
Carlos—I agree with Summer’s recommendation below (http://www.leeduser.com/comment/redirect/71714) to seek guidance from your GBCI review team. You will be expected to update all documentation affected by the change in floor area to ensure that the floor area is consistent across all credits. This may include energy models, MRp1 waste calculations, and any other credit calculations that use the gross floor area as an input.
Edgar Arevalo
Associate18 thumbs up
May 5, 2020 - 11:27 am
Hello Jon,
I am in the same pickle with modifying gross floor area during preliminary review because a previous engineer got it wrong in the first place. The link you provided does not work now. Do you have another link with the Summer's advice? If I go ahead with modifying the gross floor area, and then update all documentation affected by the change to the corresponding credits, are there any other consequences I should look out for?
Summer Minchew
Managing PartnerEcoimpact Consulting
LEEDuser Expert
170 thumbs up
May 5, 2020 - 11:59 am
Edgar, the advise was this: "I would alert your GBCI review team as to the circumstances of the project size modification and ask for project specific guidance. This can be done through the Help tab at LEEDonline."
Edgar Arevalo
Associate18 thumbs up
May 5, 2020 - 12:59 pm
is there a speedier way to contact the GBCI review team other than e-mail via the contact us link at USGBC website?