We have an existing 45 Storey building consist of 2 basements, ground, two mezzanine, and 40 floors.
since the owner tendered a renovation & Maintenace work, replacing all the MEP systems, and big part of finishes, for all floors. excluding the exterior. First 3 floors will be used by owner team and facility management. Thus, owner decided remaining 40 floors to be used by tenants as offices rental.
Which rating system is most suitable for our case?
- the building doesn't appear to have been occupied for the last year
- the owner is replacing mechanical systems and finishes throughout the building
- the owner is only occupying 3 out of 45 floors, but owns the entire building
You should consider checking with LEED Coach (leedcoach@usgbc.org) to confirm. Kara