I have a project adminnstration question or two:
On page 1 of 3 of the credit template the initials of the Contractor are requred acknowleging that System Manual or O&M Manual has been provided to owner. Two questions:
1. Doesn't the acknowledgement of the Owner has recieved an O&M Manual make this a Construction Credit and not a Design Credit?
2. Practically speaking, how do you make the template available for the contractor to initial? Do you assign/share EQ7.1 responsibility with the Contractor?
Carrie Webster
Moseley Architects57 thumbs up
November 23, 2010 - 4:35 pm
We just ran into this same issue! In the comments on this site for LEED NC 2009 - EQc7.1 there is some discussion about this, and one comments imlplies that the O&M manual signatory was removed, but that does not appear to be the case for your project or ours. We are sending a feedback inquiry through LEED online to try to find out what to do. Not only is it inappropriate to assign the contractor to inital a design phase credit, but nowhere in the reference guide that I can find does it say that this credit will require documenting a systems/O&M manual. I hate being blindsided by something on the template that is not mentioned in the credit requirements!
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
December 8, 2010 - 8:24 am
Have you guys checked that your LEED Online forms are as up to date as possible? No BETA marking on the bottom? They don't get updated automatically....