Our project team has a question about the definition of building alteration for LEED-EB certification.
According to the reference guide, the minimum alteration “include construction activity by more than 1 trade specialty, make substantial changes to at least 1 entire room in the building, and require isolation of the work site from regular building occupants for the duration of construction are eligible.”
In order to earn the related credit such as MRC3, MRC9 and IEQC1.5, our client would like to renovate the flooring of the locker room. It is one entire room and will be isolated from regular building occupants during construction, but does it meet the requirement of “including construction activity by more than 1 trade specialty”?
If it is not, then to what extend should we suggest our client to add more construction work to make it be eligible for the application?
Many thanks!!