Hi there!

We have a situation, where a developer has a Core+Shell building under construction and the original design included to install X amount of Fan coil/Condenser units (VRF system). Tenant Finish out work would add units to the Base Building VRF system as deemed necessary. 

Now the Core+Shell Owner is considering removing most of the Fan coil /condenser units of one floor (with a possibility of all the floors) from the C+S scope and transfer that scope to the Tenant Finish out. C+S Contractor would only install the units in the common areas and those will not be powered up for factory start-up until the Tenant Improvement contractor finishes their work. 

How this will impact to the Base Building Cx Fundamental/Enhanced scope ? -

Since there will be only one outside air unit installed as part of the C+S project and the HRB/condensers will not be connected to enough FCU so units to be started-up. 

Any advise would be greatly appreciate it, since the Owner would like to make a decision soon.