We are building a new building but the site work is being performed by the landlord. Do we have to require that the landlord meet complete the documentation or is this pre-req considered out of scope and we should follow a zero lot line condition scenario?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
July 6, 2010 - 9:47 am
I am curious if others have an opinion on this, but it seems to me that if the site work is being done at the same time and basically within the scope of work of the LEED-NC construction, then it should be included in SSp1 documentation.The prerequisite is not hard to achieve and documentation should be easy to complete, whether it's by the landlord or a member of your team. See our guidance and samples above on how to do this.