Need help on this question, as I received two different sets of answers!

After submitting the Design Review for a project, a project team receives several clarification requests from the project reviewer. What should the project team do? (Choose 2)

Upload any revised documentation to LEED Online

Call the LEED reviewer to discuss the issues presented in the review comments

Delete all documents submitted with the initial review

Clearly respond to each item where the reviewer has provided technical advice

Respond to all reviewer comments within 15 business days