I'm working on a new classroom building on a university campus. The university's cleaning service picks up trash and recycling daily from all of the classrooms, hallway receptacles, etc. in each building on campus and takes it all to a central location where it processed. With this in mind, it doesn't make sense to have a central location for sorting of recyclables in this new building as it won't be used, and the central trash/recycling center on campus is not a part of our project. How do I handle this prerequisite?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11474 thumbs up
August 26, 2017 - 4:48 pm
That's unusual. To fend off any objections from GBCI that could cause problems if they came too late, I would contact GBCI to clear this approach. It sounds like it makes sense, but it is, in my experience, unusual.