If the mechanical system is not capable of moving the required volume of air in a reasonable amount of time, establish a plan for credit compliance that either includes using temporary fans or IAQ testing.
Once the mechanical system is confirmed, establish the required time required for flush-out with the mechanical engineer (which should be a relatively simple calculation) and coordinate the flush-out with the contractor’s construction schedule.