The Whole Building Calibration Simulation requires information about the instruments that enable the project to monitor the categories listed in the IPMVP.
To achieve this credit under Option D, the M&V plan must be able to identify specific building performance issues. A BMS or submetering will be able to build this capacity into the system.
The BMS should be set up to collect data that will allow fair comparison between actual and predicted energy use. For example, since weather patterns are factored into the energy model, the BMS should capture these, along with other parameters such as operating schedule, occupancy
Run a preliminary energy model. If an energy model is being developed for EAc1: Optimize Energy Performance, the model can be used as the energy use baseline for the M&V plan. Otherwise a new model may be run to determine the baseline energy use. The actual energy use will be compared to this baseline.