Carefully examine the sequencing of material installation before construction begins. Schedule installation to protect absorptive materials from construction pollution. For example, do not store or install acoustic ceiling tiles before painting occurs or flooring products are installed because the ceiling tiles will absorb the off-gassing paint or floor adhesives and will contaminate the air over a longer time period.
These practices may be slightly time-consuming, but will help to create a healthier working environment for all the construction workers onsite on a daily basis. Communicating this point frequently to everyone on the site can help to build compliance.