If separation is occurring off-site at a comingled or mixed-debris processing plant, make sure the processor or recycling facility can provide documentation for the amount of waste processed, by weight or by volume, as agreed, as well as a diversion rate from the facility. This could be either a project-specific diversion rate supplied by the facility, or a letter from the state regulating body with the facility's average rate of recycling.
Value engineering and other factors can result in design changes that eliminate certain energy features relevant to the credit. As this compliance path is prescriptive, your project cannot afford to drop even one listed item. Although perceived as high-cost, prescriptive requirements lower energy costs during operation and provide a simple payback structure.
Finalize all design decisions and confirm that you’ve met all of the prescriptive requirements. Your team must document the checklist with relevant project drawings, including wall sections, specifications, and the MEP drawing layout.