Ensure that you include time for building flush-out or testing in the construction schedule as early as possible.For Path 1 (continuous flush-out), 14,000 ft3 of air must be moved while not exceeding 60% relative humidity and 60ºF. This may take up to two

Ensure that you include time for building flush-out or testing in the construction schedule as early as possible.

For Path 1 (continuous flush-out), 14,000 ft3 of air must be moved while not exceeding 60% relative humidity and 60ºF. This may take up to two weeks depending on system capacity.
For Path 2, a continuous flush-out of 3,500 ft3 of air must be completed and then a phased flush-out until 14,000 ft3 of air has been moved. This duration varies: 3,500 ft3 may take just a few days, but the remaining phased flush-out may take several weeks.

If not completed in pre-construction, your IAQ management plan should be developed by the general contractor and incorporate input from your entire project team, specifically the technical requirements for flush-out identified by the mechanical engineer a

If not completed in pre-construction, your IAQ management plan should be developed by the general contractor and incorporate input from your entire project team, specifically the technical requirements for flush-out identified by the mechanical engineer and any special scheduling required by the building owner or tenants. The plan should be shared with the whole project team, including all subcontractors who will be working with any interior materials and fittings.