Hi All,
I am in a state of dilemma for submitting the building envelope parameters to the design team during tender stage of a project. The U values and SHGC factors are being asked by architect team to compare proposed envelope design against ASHRAE 90.1 in every tender project. And the same U value and SHGC factors are being taken forward by HVAC design team to size the systems in HAP.
In this case, being from the sustainability team, do we refer the values based on prescriptive compliance path or do we directly refer the baseline values as per Appendix G in ASHRAE 90.1?
Please Note: The initial proposed envelope details are shared to us for comparison.
Your clarifications & suggestions are greatly appreciated.
For the EAp2 prereq in v4.1 you can demonstrate compliance with 90.1-2016 via prescriptive, ECB in Section 11 or PRM in Appendix G. Which of these paths is the design team planning to use for LEED?
If you're going perscriptive, then you'll need to be at least as good as the glazing tables for your climate zone in the envelope tables in Section 5.5 (if we ignore Envelope Tradeoffs in 5.6).
If you're using a performance path, then the glazing in the model's baseline is from Table 5.5x for ECB or Table G3.4-x for PRM.
You won't want to tell the design team the values in Appendix G as those are for the 2004 stable baseline and you'll have to beat those by a decent margin, so don't send the team those as it will misled them.