Once the performance period closed for our project, we realized that we did not divert 75% of ongoing waste as required by the prerequisite. Can we perform the alternative waste stream audit now, after the performance period has ended?
Thank you.
Forum discussion
EBOM-v4 MRp1: Ongoing purchasing and waste policy
Once the performance period closed for our project, we realized that we did not divert 75% of ongoing waste as required by the prerequisite. Can we perform the alternative waste stream audit now, after the performance period has ended?
Thank you.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Randi B.
Sustainability Consultant/PMMay 25, 2023 - 4:45 pm
I realize this response is late but to address for anyone else who may have this question - my understanding is that any action taken after the performance period would either be considered ineligible to be used for compliance or the performance period would need to be extended to capture it. This is why a pre-performance period is recommended in the reference guide, to identify these kind of issues and allow the project team to pivot their approach for the actual performance period.