Fundamental Commissioning requires the CxA to review the OPR and BOD and design documents.
Why does the Fundamaental Commissioning LEED Online template require the CxA to list the "Date of CxA review of CONSTRUCTION documents"?
For a building with individual systems per unit, does every single system need to be commissioned?
What kinds of projects must the CxA demonstrate experience on?
What level of authority does the CxA have towards correcting inaccurate or erroneous construction?
Can the CxA be a member of the design or construction team?
Forum discussion
NC-v4 EAp1:Fundamental commissioning and verification
Fundamental Commissioning requires the CxA to review the OPR and BOD and design documents.
Why does the Fundamaental Commissioning LEED Online template require the CxA to list the "Date of CxA review of CONSTRUCTION documents"?
LEEDuser is supported by our premium members, not by advertisers.
To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
The credit language also indicates the Cx Provider develops the OPR and BOD. In the next paragraph, we just review them.
If you ask ASHRAE, we review it, we verify it, we may even provide a format for it but we're not responsible for creating it.
https://www.ashrae.org/file%20library/about/new%20hq/ashrae-opr-attachment-to-design-services-rfp-signed.pdf