Forum discussion

CI-v4 EQc4:Indoor air quality assessment

Multi floor Office Building - Can each floor be flushed as it gets installed?

Dear colleagues,

We have a multi-floor Office Building.  Can each floor be installed with furniture then flushed, starting at the ground level then moving up.  This is to accommodate a tight schedule.  Each floor has fan rooms.

Thank you for your guidance.

 

 

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 04/12/2021 - 22:40

Hi Susan, See if this post from the NC version of this credit is helpful: http://leeduser.buildinggreen.com/forum/iaq-testing-3
(also let me know if this link doesn't work...having a hard time posting links lately)