We are currently designing Aquatic center near Pioneer High School. there are proposed/Adopted Bike Network passing our site. is that goint to be acceptable? or the only way we can get points is to have existing Bike Lane/Trails?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Summer Minchew
Managing PartnerEcoimpact Consulting
LEEDuser Expert
170 thumbs up
June 3, 2021 - 3:26 pm
The LEED v4.1 Reference Guide states, "Planned bicycle trails or lanes may be counted if they are fully funded by the date of the certificate of occupancy and are scheduled for completion within three years of that date."