We've received our final Design Review but want to add a design credit and correct a credit that was denied. I was going to download a copy of the new credit to work on but everything is locked until I choose to either Accept or Appeal. What is the difference in these choices if I can add a Design credit at the preliminary construction review?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
February 18, 2020 - 4:33 pm
You can add the design credit in the construction review phase. To correct the credit you will need to file an appeal.
Jeannie Rueter
Green Building AnalystAusonio Incorporated
3 thumbs up
February 18, 2020 - 5:46 pm
Thanks for responding so quickly! That's what I needed to know!