Hi, 

We are working on LEED project as general contractor in middle east which is registered under LEED new construction. 

As a part of compliance with SSP1, we have implemented number of ESC measures onsite such as erosion & pollution control due to wind applicable during construction stages. However, consultant raising issues of use of plastic, scaffolding/material storage arrangements, blocks/aggregates storage on a daily basis as a part of non compliance to SSP1 LEED.

Appreciate if you please advise if these are really SSP1 LEED issues. If not how we can convince consultant.