Our project is a complete interior renovation of an existing facility on a college campus. The project building has an established site that is turf grass, trees, and shrubs but no work is planned on the site, our LPB is essentially the building perimeter as all the work is being done inside. The only work planned on the site is to return anything disturbed back to the way it was.
Does this make the WEp1 prerequisite not applicable to our project?
emily reese moody
Sustainability Director, Certifications & ComplianceJacobs
LEEDuser Expert
476 thumbs up
July 16, 2020 - 2:46 am
As far as I know, it still applies to whatever vegetation is within your project boundary, which would include site disturbance areas. If there's no permanent irrigation there, then you're good.