NC-2009 EAc5:Measurement and Verification

Phased project implementation

We have a phased higher education project in which a new building addition will be built first, then the existing buildings will be renovated and open a year later. Does the college need to contract for two post-occupancy performance recordings, one for each phase, or can they wait and do the entire project following the overall project completion?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Sun, 09/15/2019 - 21:47

They can wait and do it all at once. Just say so in the M&V Plan