Hi Everybody,
When I was trying to fill out the Minimum Energy Performance Data Center Calculator, I was confused about ''IT load influenced by project(%)''.
''IT load influenced by project (%)'' refers to the expected planning of the IT equipment ratio during the certification period? (Example: If the project will planning and installing all IT equipment in the scope of certification, I should fill in 100%.)
How is this different from ''Startup IT load (kW)''?