Background Considerations:

My Project a registered mixed use facility per code and USGBC is an ideal Industrial, Commercial and Institutional (ICI) Building all in one, has satisfied provisions for the Option 1. Electric Vehicles and Charging Station under New Construction and also Satisfies the provision for Option 1. Alternative -fuel Vehicles (both accorded 1 point each.)

In applying for various other credit categories and items, the project has utilized this mixed use variable; for example, in the calculation at determining the Aggregated parking for LTc7 - Reduced Parking Footprint the mixed use identity was brought to bare. 

Question:

As stated above, requirements per Option 1 for both New Construction and Warehouse and Distribution centers have been provided for... Does this not qualify the project for 2 points rather than 1 Point?! (I see there is No Exceptional Performance called out for this credit.) This might well be a reason to request one here.

Thanks all for the feed-back, the scope for the project has deep environmental considerations and this extra effort and expense should not go un-noticed.