NC-2009 MRc7:Certified Wood

NEW Non FSC Certified Wood used as Redwood Header installed under the ground outside the building

Is the NEW Non FSC Wood  Header installed underground outside the building not part of the NEW Wood Baseline in MRC7 Certified Wood?

 

Please advise.

Thanks..

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 11/15/2018 - 05:00

Is it part of the building project scope? If it is, then it is part of the new wood on the project.