Hi all
My project is a green field site apart from utility services (water and electric) which run underground through a portion of the site for neighbouring buildings.
Could this be considered previously developed?
Thanks in advance.
Forum discussion
NC-v4 LTc2: Sensitive land protection
Hi all
My project is a green field site apart from utility services (water and electric) which run underground through a portion of the site for neighbouring buildings.
Could this be considered previously developed?
Thanks in advance.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Blake Jackson
Director of SustainabilityNORR
LEEDuser Expert
7 thumbs up
September 7, 2018 - 7:10 pm
Based on this information, I would assess that the project site is still a greenfield. The goal of LEED is to support smart-growth principles, particularly around densification and infilling.