Is a drawing review of the building envelope required by EAp1 Fundamental Cx if Enhanced Option 2 is not being pursued?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
"The OPR must include all systems to be commissioned plus the building envelope, even if full envelope commissioning is not pursued." and "The BOD must include all systems to be commissioned plus the building envelope, even if full envelope commissioning is not pursued. The project engineer, architect, structural engineer, and other team members must work together to document building envelope thermal performance, load-bearing capabilities, and construction."
So, it sounds like we have to at least talk about it, but it's not required to actually be commissioned?