hi i'm new on LEED,
can we perform preliminary review of uploaded documents even if other requirements aren't completed?
Forum discussion
NC-v4 MPR1: Must be in a permanent location on existing land
hi i'm new on LEED,
can we perform preliminary review of uploaded documents even if other requirements aren't completed?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
December 12, 2017 - 5:14 pm
Jade, you can submit partial documentation as part of a "Design Review," which would take place before the Construction review of complete documentation.
You can get a basic read on this by reading the LEED Reference Guide.