In this project, we have one office, two plants signed up for LEED Campus. Cooling & Heating for these plant buildings comes from Chillers & Boilers located in centrally located plant in the campus. This centally located plant also serves cooling/heating to some other buildings in the campus which is not included in the LEED boundary. The office biulding (3rd one in the LEED boundary) is cooled & heated by its own systems located inside the building.

In this situation, does the DES modeling method apply? Can we do all the buildings seperately following 90.1-Appendix G w/o any addendum? Are there any USGBC document which describes the conditions for the DES criteria?