CS-v4 EAc5:Renewable energy production

PPA as renewable energy production?

Hi! In the requirement for EAc5 (BD+C) it is stated: "The use of solar gardens or community renewable energy systems is allowed if both of the following requirements are met. 1)The project owns the system or has signed a lease agreement for a period of at least 10 years. 2) The system is located with the same utility service area as the facility claiming the use." Can you get credits from a Wind-PPA? And what does it mean with "the same utility service area"? Is there any specific distance for off site wind-PPA (like kilometres / Miles)?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 08/28/2017 - 13:41

Yes I would think that a wind PPA would qualify. In the US we have regional electric utility service territories. Some are vast, some are small so there is no specific distance.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.