Looking to confirm:
We are using subgrade Fill for our building project that was procured from an on-site location.
As per the above, site materials can apply to MR 4 and 5 percentages, as long as the cost for the fill (which we are using a processing cost x tonnage) is applied consistently throughout the project.
The quantities involved may greatly improve our percentages of recycled and regional content, and I wanted to confirm that Fill was an allowable material.
It certainly fulfills the spirit of the credits, if not only the letter of them.
Thank you.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
August 26, 2017 - 7:09 pm
What's recycled about this fill?