Hi
We are currently busy with LEED documentation of a manufacturing facility that is under operation for a year now. However, due to contractual issues and delays, a few of the systems such as rain water harvesting, water treatment plant are yet to be commissioned. Additionally, the installed motors need to be replaced with those that were specified in OPR. These actions will take anywhere upto 3 months however the project team and the owner would like to submit the documentation.

My question is, is there a limit to the number of systems that can be put on hold for commissioning? CxA and contractors have completed FPT for all the other HVAC components and lighting controls except the ones listed above. Can we describe these pending items under the issues log and resolution report ?

Thanks!