Forum discussion

EBOM-2009 SSc7.2:Heat Island Reduction—Roof

Green Roof Installation After PC for C&S

Hi, I have a Core & Shell Project that will be installing a Green Roof after the Post Construction stage (i.e. 6 months after C&S Completion) Can such credits as, SSc7.2 Heat Island Effect - Roof, be awarded under the Core and Shell Assessment once a legal document confirms that the Green Roof will be installed in 6 months?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 04/01/2016 - 19:26

Hi Francis, I think you might get a better response if you post this question under Core & Shell.