I am working on a CS project and the drawings do not have any planned ref equipment since this will be at the tenants discretion to decide at a later date.
If our plans do not include ref equipment, are we still able to receive points for this credit? What is required to submit for certification if we do not have this equipment included in the drawings?
Thanks.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
January 26, 2016 - 12:53 pm
Alanna, this is covered on page 15 of the LEED Reference Guide. Basically you can only count what's in your CS scope to earn the credit, unless you use a tenant lease agreement.