Shall the mandatory efficiency of section 6.4 (Tables 6.8.1) be verified also for a chiller that works as backup system (the chilled water is provided in normal conditions by district cooling)?
Best Regards
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5869 thumbs up
July 31, 2015 - 9:26 am
Probably a good idea. If it will not normally operate at all and function as an emergency back up then you may be able to argue that it would not have to meet it.