CS-2009 MRc5:Regional Materials

Concrete Formwork

Should I include temporary materials, such as concrete formwork and shoring, in the documentation for MRc5? Thanks!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 06/24/2015 - 23:53

You cannot include temporary materials in any of the calculations for MR Credits MRc3, MRc4, or MRc5. The LEED-2009 BD+C Reference Guide, under the “Requirements” heading for each of these credits, says, “Include only materials permanently installed in the project.” You will find the same language in the CS Rating System. Follow this link for a discussion on the NC MRc4 page: http://www.leeduser.com/comment/redirect/53164.