All, new to energy modeling and reviewing the EAp2 online template trying to figure out the required inputs and reports for the Target Finder section, Design vs Target. For which are the Baseline and Proposed model results used?
Project types range from office to manufacturing, for international and U.S. locations, so guidance on each combination is appreciated. The FAQs above and checkbox in the template indicate no inputs are necessary for unsupported building types and international projects. Please confirm.
Thanks, Rock
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5911 thumbs up
March 25, 2015 - 8:44 pm
Do what the form says. The proposed modeling results are used in Target Finder. The purpose here is to make sure you are doing a reality check on your energy modeling results. Do they make sense? If you have a typical just above code project it would likely not score below a 75 or above a 90.